Program controls

Budget

Approved budget, commitments, spend, forecast, contingency, and Project-level variance.

$580.0MApproved budget$579.5MForecast$500KFavorable

Program financial position

Current approved budget$580,000,000Latest reporting date Jul 15, 2026
Committed$344,100,00059.3% of budget
Spent to date$184,900,00031.9% of budget
Forecast at completion$579,500,000Current program forecast
Forecast variance$500,000Favorable
Contingency remaining$22,200,000Across reported Projects
Pending changes$0Not yet approved

Exception focus

Forecast pressure

Projects currently forecast above their approved budget are surfaced first.

Project detail

Budget by Project

Compare current approved budget and forecast at completion across the program.

As of Jul 15, 2026
Current budget$184,000,000
Committed$160,500,000
Spent$94,500,000
Forecast$182,400,000
Variance$1,600,000
Contingency$5,600,000

Forecast remains actively managed through project contingency and program reserve.

As of Jul 15, 2026
Current budget$126,000,000
Committed$112,800,000
Spent$58,600,000
Forecast$124,700,000
Variance$1,300,000
Contingency$4,300,000

Forecast remains actively managed through project contingency and program reserve.

As of Jul 15, 2026
Current budget$72,000,000
Committed$9,100,000
Spent$4,200,000
Forecast$71,600,000
Variance$400,000
Contingency$3,800,000

Forecast remains actively managed through project contingency and program reserve.

As of Jul 15, 2026
Current budget$88,000,000
Committed$17,400,000
Spent$6,900,000
Forecast$89,700,000
Variance-$1,700,000
Contingency$2,900,000

Forecast remains actively managed through project contingency and program reserve.

As of Jul 15, 2026
Current budget$46,000,000
Committed$2,200,000
Spent$1,100,000
Forecast$45,800,000
Variance$200,000
Contingency$3,500,000

Forecast remains actively managed through project contingency and program reserve.

As of Jul 15, 2026
Current budget$64,000,000
Committed$42,100,000
Spent$19,600,000
Forecast$65,300,000
Variance-$1,300,000
Contingency$2,100,000

Forecast remains actively managed through project contingency and program reserve.